How to install press-fit pipework for ACR systems
The popularity of press-fit technology continues to grow as installers increasingly favour its ease of installation, consistent joint quality, removal of the need for hot works and superior scorch-free finish.
Factors including the ongoing skills shortage and the subsequent need for installers to maximise their productivity on site and minimise callbacks, combined with more stringent health and safety regulations, have all contributed to this growth.
In the air conditioning and refrigeration (ACR) market, the adoption of press-fit products has been accelerated by installers working on supermarket, commercial refrigeration and data centre projects.
Applications for press fittings in ACR
Press fittings are suitable for use in ACR applications that typically see higher working pressures of up to 48 bar, but specialist fittings need to be used.
Given the higher working pressures involved with ACR applications, fitting performance and the way in which they are installed are critically important. When choosing air conditioning or refrigeration press fittings, installers should look for performance criteria similar to those provided in the table below for Instantor R Press:
Main considerations
The following data relates to Instantor R-Press fittings and is provided as a guide only. If other manufacturers’ fittings are used, it is important to refer to their specific instructions.
Minimum distance between pressings, and insertion depth
Due to the reforming of the tube when it is pressed, the following should be allowed between each fitting:
Minimum distance between press fittings and existing brazed joints
The following minimum distances are advised from press fittings to existing brazed joints, once all hot works are complete and cooled:
Testing and commissioning
Testing and commissioning of ACR systems should be carried out in accordance with the requirements specified in BS EN 378-2:2016 (Refrigeration systems and heat pumps) and Assimilated Regulation (EU) No 517/2014 (the GB F-gas Regulation).
Installation and storage
ACR press fittings are usually compatible with V profile jaws and many are compatible with press tools from a number of manufacturers.
Fittings should be kept in sealed bags as supplied by the manufacturer in order to prevent the O-rings from drying out.
Achieving best practice installations
Instantor provides a comprehensive installer competency training programme. For ACR press fittings, the following steps should be followed in order to achieve best practice:
1. Cut the tube completely square, checking for any defects and scratches which may affect joint integrity.
2. Deburr the tube using a deburring tool, making sure both the inside and outside are free from sharp edges.
3. Clean the tube end thoroughly using a general purpose scotch cloth or pad in a rotating motion. Ensure the ends are free from scratches, oxidation, dirt and debris.
4. Check again for defects and if any deep scratches or imperfections remain, cut the tube back and repeat steps two and three.
5. Ensure the O-ring is seated and that the fitting matches the tube size. Verify all O-rings are present and undamaged.
6. Insert the tube into the depth gauge and mark the insertion depth. Insert the tube into the fitting. The tube needs to be fully inserted into the fitting stop end. Marking the tube will allow any movement of the fitting to be seen before pressing.
7. Align jaws squarely on the fitting. Ensure the pipework is correctly aligned prior to pressing and that the correct size jaw is inserted into the tool. Jaws must be placed squarely on the fitting, locating the groove over the O-ring. The O-ring on the fitting should sit centrally in the groove on the jaw.
8. Depress and hold the press tool button to complete the pressing cycle.
9. Release the jaw.
10. Mark the completed joint after pressing. This enables joints to be inspected easily before testing and insulating the pipework.
Installer benefits
When compared with traditional methods such as brazing, press fittings offer a number of distinct benefits.
First, the flame-free installation avoids the need for ancillaries such as torches, heat mats, fire permits, time-consuming fire watches and the risks of fire on site. Access to site is also made easier without having to handle and carry additional equipment and gas bottles.
Because no heat is applied when making the joint, nitrogen purging is not required for the jointing process itself, again reducing project times and costs. In addition, field tests have shown that press fittings are up to 35% faster than traditional methods.
Calibrated press tools provide exceptional joint quality, repeatability and reliability which offers installers, contractors and project owners an additional layer of security.
Three-point press designs are intended to improve joint integrity by applying compression at defined points around the fitting over even the largest of sites. Two press points are positioned either side of the bead and the third is used to compress the O-ring to provide secure and reliable joints. High-quality HNBR O-rings also provide secure, leak-free joints when pressed.
It is also worth remembering that press-fit products are proven, have been trusted by the trade for two decades, and hundreds of thousands of projects have been completed successfully.